The H-1 Shoulder Work and PCCP Pavement Rehabilitation will be completed in 3 phases. Due to the success of the first phase of the project, an additional phase was added in late 2018 to further rehabilitate the H-1 Freeway.

Phase 1 was completed in the Fall of 2018.

Phase 2 will begin in the Fall of 2018 and end in the Spring of 2020.

Phase 3 will begin in early Summer 2019.

Phase 1 will consist of pavement rehabilitation of approximately 2.0 miles of H-1 East bound and West bound lanes.

Phase 2 is the widening of the shoulder for an additional 1 mile of the H-1 East bound between the Waimalu Viaduct and the Aiea Off Ramp. Highway lighting, drainage systems upgrades and safety upgrades to the highway shoulder will also continue as part of Phase 2.

Phase 3 work includes the installation of precast concrete panels in 3 additional areas. Two of these areas are located at the Pearl City Viaduct, both East bound and West bound, while the third rehab location is on H-1 East bound near the Aiea/Stadium off-ramp.

Project<br />
Overview
Project
Overview
Construction<br />
Schedule
Construction
Schedule
Construction<br />
Updates
Construction
Updates
Traffic<br />
Management
Traffic
Management

For additional up to the minute Oahu traffic info including: Incidents, Cameras, Drive Times, Travel Links, Weather Links and Social Media; go to: goakamai.org.

Start typing and press Enter to search