Weekly Lane Closure Schedule (Week of 1/13/19)

Date Closure Purpose
Sunday (1/13)
  • No lane closures scheduled
Monday (1/14)
  • H-1 eastbound shoulder lane closed from near Waimalu viaduct to Aiea pedestrian overpass from 9:00 am to 7:00 pm.
  • H-1 westbound no lane closures scheduled.
Shoulder widening work
Tuesday (1/15)
  • H-1 eastbound shoulder lane closed from near Waimalu viaduct to Aiea pedestrian overpass from 9:00 am to 7:00 pm.
  • H-1 westbound no lane closures scheduled.
Shoulder widening work
Wednesday  (1/16)
  • H-1 eastbound shoulder lane closed from near Waimalu viaduct to Aiea pedestrian overpass from 9:00 am to 7:00 pm.
  • H-1 westbound no lane closures scheduled.
Shoulder widening work
Thursday  (1/17)
  • H-1 eastbound shoulder lane closed from near Waimalu viaduct to Aiea pedestrian overpass from 9:00 am to 7:00 pm.
  • H-1 westbound no lane closures scheduled.
Shoulder widening work
Friday (1/18)
  • H-1 eastbound shoulder lane closed from near Waimalu viaduct to Aiea pedestrian overpass from 9:00 am to 11:59 pm.
  • H-1 eastbound single right lane closed from Waimalu viaduct to Kaonohi overpass from 10 am to 6:30 pm.
  • H-1 eastbound two right lanes closed from Pearl City viaduct to Aiea off-ramp from 6:30 pm to 6:30 am. Third right lane closed from 7:30 pm to 6:00 am. Shoulder lane closed.
  • H-1 westbound no lane closures scheduled.
Shoulder widening work – paving
Saturday (1/19)
  • H-1 eastbound shoulder lane closed from near Waimalu viaduct to Aiea pedestrian overpass from 12:00 am to 11:59 pm.
  • H-1 eastbound two right lanes closed from Pearl City viaduct to Aiea off-ramp from 7:00 pm to 9:00 am. Third right lane closed from 8:00 pm to 7:30 am. Shoulder lane closed.
  • Note – The 2-3 right lane closures are contingent on the previous day’s work and may not be needed if all work can be completed beforehand.
  • H-1 westbound no lane closures scheduled.
Shoulder widening work – paving

Weekly Lane Closure Schedule (Week of 1/20/19)

Date Closure Purpose
Sunday (1/20)
  • H-1 eastbound shoulder lane closed from near Waimalu viaduct to Aiea pedestrian overpass from 12:00 am to 4:00 am.
  • H-1 eastbound two right lanes closed from Pearl City viaduct to Aiea off-ramp from 6:30 pm to 4:00 am. Third right lane closed from 7:30 pm to 4:00 am. Shoulder lane closed.
    Note – The 2-3 right lane closures are contingent on the previous day’s work and may not be needed if all work can be completed beforehand.
  • H-1 westbound no lane closures scheduled.
Shoulder widening work – paving
Monday (1/21)
  •  No lane closures scheduled.
Tuesday (1/22)
  • H-1 eastbound shoulder lane closed from near Waimalu viaduct to Aiea pedestrian overpass from 9:00 am to 7:00 pm.
  • H-1 westbound no lane closures scheduled.
Shoulder widening work
Wednesday  (1/23)
  • H-1 eastbound shoulder lane closed from near Waimalu viaduct to Aiea pedestrian overpass from 9:00 am to 7:00 pm.
  • H-1 westbound no lane closures scheduled.
Shoulder widening work
Thursday  (1/24)
  • H-1 eastbound shoulder lane closed from near Waimalu viaduct to Aiea pedestrian overpass from 9:00 am to 7:00 pm.
  • H-1 westbound no lane closures scheduled.
Shoulder widening work
Friday (1/25)
  • H-1 eastbound shoulder lane closed from near Waimalu viaduct to Aiea pedestrian overpass from 9:00 am to 11:59 pm.
  • H-1 eastbound single right lane closed from Waimalu viaduct to Kaonohi overpass from 10 am to 6:30 pm.
  • H-1 eastbound two right lanes closed from Pearl City viaduct to Aiea off-ramp from 6:30 pm to 6:30 am. Third right lane closed from 7:30 pm to 6:00 am. Shoulder lane closed.
  • H-1 westbound no lane closures scheduled.
Shoulder widening work – paving
Saturday (1/26)
  •  H-1 eastbound shoulder lane closed from near Waimalu viaduct to Aiea pedestrian overpass from 12:00 am to 11:59 pm.
  • H-1 eastbound two right lanes closed from Pearl City viaduct to Aiea off-ramp from 7:00 pm to 9:00 am. Third right lane closed from 8:00 pm to 7:30 am. Shoulder lane closed.
  • Note – The 2-3 right lane closures are contingent on the previous day’s work and may not be needed if work can be completed beforehand.
  • H-1 westbound no lane closures scheduled.
Shoulder widening work – paving

*Note: The nighttime closures are needed to facilitate the relocation of the drilling platform.  These lane closure dates are flexible and will be confirmed the day prior if needed.

Should you have any questions or concerns, please contact (808) 483-2570.