Traffic Management

Currently, lane closures to be expected include day closures for the shoulder lane, H-1 East bound. Night closures for H-1 East bound between the H-1 and H-2 merge and the Aiea Off Ramp.

Night closures are expected for H-1 West bound lanes between the Halawa interchange and the Pearl City Off Ramp.

Weekly Lane Closure Schedule (Week of 7/22/18)

Date Closure Purpose
Sunday (7/22)
  • No lane closures scheduled
Monday (7/23)
  • H-1 eastbound lanes closed near Pearl City viaduct to Aiea pedestrian overpass. Shoulder lane closed.
    • Two lanes closed at 6:30 PM, 3rd lane closed at 7:30 pm. All reopen by 4:00 AM. Lanes will be shifted from left to right between work zones.
  • H-1 westbound lanes closed near Halawa interchange to Pearl City viaduct. Shoulder lane open.
    • Two left lanes closed at 8:00 PM. 3rd left lane closed at 9:00 pm. All reopen by 3:00 AM.
PCC rehab panel setting, grouting, and median pour back
Tuesday (7/24)
  • H-1 eastbound lanes closed near Pearl City viaduct to Aiea pedestrian overpass. Shoulder lane closed.
    • Two lanes closed at 6:30 PM, 3rd lane closed at 7:30 pm. All reopen by 4:00 AM. Lanes will be shifted from left to right between work zones.
  • H-1 westbound lanes closed near Halawa interchange to Pearl City viaduct. Shoulder lane open.
    • Two left lanes closed at 8:00 PM. 3rd left lane closed at 9:00 pm. All reopen by 3:00 AM.
PCC rehab panel setting, grouting, and median pour back
Wednesday  (7/25)
  • H-1 eastbound lanes closed near Pearl City viaduct to Aiea pedestrian overpass. Shoulder lane closed.
    • Two lanes closed at 6:30 PM, 3rd lane closed at 7:30 pm. All reopen by 4:00 AM. Lanes will be shifted from left to right between work zones.
  • H-1 westbound lanes closed near Halawa interchange to Pearl City viaduct. Shoulder lane open.
    • Two left lanes closed at 8:00 PM. 3rd left lane closed at 9:00 pm. All reopen by 3:00 AM.
PCC rehab panel setting, grouting, and median pour back
Thursday  (7/26)
  • H-1 eastbound lanes closed near Pearl City viaduct to Aiea pedestrian overpass. Shoulder lane closed.
    • Two right lanes closed at 6:30 PM, 3rd right lane closed at 7:30 pm. All reopen by 4:00 AM.
  • H-1 westbound lanes closed near Halawa interchange to Pearl City viaduct. Shoulder lane open.
    • Two center lanes closed at 8:00 PM. 3rd center lane closed at 9:00 pm. All reopen by 3:00 AM.
PCC rehab panel setting, grouting, profilographing, and grinding
Friday (7/27)
  • H-1 eastbound lanes closed near Pearl City viaduct to Aiea pedestrian overpass. Shoulder lane closed.
    • Two right lanes closed at 6:30 PM, 3rd right lane closed at 7:30 pm. All reopen by 6:30 AM.
  • H-1 westbound lanes closed near Halawa interchange to Pearl City viaduct. Shoulder lane open.
    • Two center lanes closed at 7:30 PM. 3rd center lane closed at 9:00 pm. All reopen by 10:30 AM.
PCC rehab panel setting, grouting, profilographing, and grinding
Saturday (7/28)
  • H-1 eastbound lanes closed near Pearl City viaduct to Aiea pedestrian overpass. Shoulder lane closed.
    • One right lane closed at 6:00 PM, 2nd right lane closed at 7:00 pm, 3rd right lane closed at 8:00 PM. All reopen by 10:30 AM.
  • H-1 westbound lanes closed near Halawa interchange to Pearl City viaduct. Shoulder lane open.
    • Two center lanes closed at 6:00 PM. 3rd center lane closed at 9:00 pm. All reopen by 12:30 PM.
PCC rehab panel setting, grouting, profilographing, and grinding

*Note: The nighttime closures are needed to facilitate the relocation of the drilling platform.  These lane closure dates are flexible and will be confirmed the day prior if needed.

Should you have any questions or concerns, please contact (808) 483-2570.

Start typing and press Enter to search